|
Click here for a print friendly 60k PDF version
By: Lorne MacDonald,
PopWare Inc.
I’ve read
and seen a lot of material about advanced maintenance
scheduling techniques, but the reality is that most
maintenance people are still struggling with the basics.
As a former
Operations/Maintenance Coordinator who was sick and
tired of operating in a reactive fire-fighting mode, I
understood potential benefits of proper maintenance
scheduling - the challenge was getting everyone on the
same page. Industry experts suggest that in order to
move from reactive to proactive maintenance, at least
80% of the work should be planned on a weekly basis and
compliance to this schedule should be at least 90%.
For many,
attaining this level of scheduling and execution of
planned maintenance work is an imposing challenge. I
too was a skeptic. I had seen my maintenance
organization fall into a quagmire of never-ending
emergency work and constantly struggling to keep our
heads above water. Scheduling planned work seemed like
a distant planet. But this was about to change.
A new
maintenance manager was hired and his first decree was
that planned preventive maintenance (PM) work was going
to be the order of the day. When creating weekly
schedules we had to schedule all due PM’s first and then
distribute the remaining man-hours according to
priority. Having grown accustom to the daily regime of
fire fighting maintenance activities, I saw this as
nothing more than a motherhood statement that was not
achievable; however, the new manager had other plans.
His first
order of business was to sit with Operations and explain
what he was trying to do and the potential benefits the
Operations group could achieve. His plan was to involve
the Operations group in performing routine repetitive
PMs as part of their normal rounds. While doing area
walk-downs, Operators could check lubrication globes to
ensure oil was present and replace it if it was down.
They could also perform visual inspections as well as
touch and feel components for heat, vibration, abnormal
noise, smell, and any process leakage. As a result,
Operations started playing a more active role in
ensuring the proper performance of their equipment.
They would inspect safety guards around couplings and
shafts and would report any abnormalities to the Shift
Mechanic or Shift Electrician who would determine the
severity. They would also set up air blowers to aid a
hot piece of equipment if the Shift Mechanic was busy on
another job. They would even change out filters on air
supply coolers for key motors. A new policy also came
into place that anyone could enter a request for work.
No longer was this the realm of Maintenance or
Production Supervisors, anyone could initiate the
procedure.
Utilizing a
team approach, monthly meetings were held involving
representatives from Operations, the Operations
Superintendent, an Operations/Maintenance coordinator,
Planner, Maintenance Supervisor, Maintenance Area
Technician, E&I Supervisor, E&I Area Technician, Area
Engineer, Process Control Technician, and Quality
Control Technician. At these meetings a process was
established for reviewing the PM program. PM Jobs were
reviewed for suitability to the current operating
conditions that existed in the plant. Many of these PMs
were the original Manufacturers recommended PMs and the
frequencies were reviewed to determine if they were
still relevant. Could a weekly, or monthly PM become a
3-month PM or a yearly PM? Could weekly visual
inspections be handled by Operations when it came to
equipment such as HVAC? Maintenance would still be
required to attend to major PM’s such as semi-annual
inspections and when Operations detected a discrepancy
from the expected norm, Maintenance would handle the
subsequent work order.
As a result,
maintenance slowly but steadily moved from a reactive to
a proactive mode and maintenance efficiency was
drastically improved. Equipment availability and
reliability increased and downtime and all its inherent
costs decreased. Schedule compliance was consistently
around 90% and, when it wasn’t, the reason could be
easily identified and documented.
The Key
Ingredients
Communication is key to successful maintenance
scheduling – this involves everyone from the Planner,
Scheduler, Maintenance Supervisor, Craftsman, Storeroom
personnel, Operations Superintendent, to the Operator
who is responsible to have the equipment secure and
ready for maintenance. Any breakdown in this
communication diminishes the probability of success.
The role of
each stakeholder needs to be clearly identified – what’s
expected from them and what do they bring to the table:
Planner
– ensures the work is properly planned with trade
requirements, stores material, direct purchase material,
and specialty service(s) identified on the work order.
Any safety concerns or requirements are documented, as
is the description of the work to be carried out.
Scheduler
– ensures that the trades are available to conduct the
work during the schedule duration. The Maintenance
Supervisor attends to the specifics as to
who-what-where-when. The Scheduler also ensures that the
material and/or services are available. He also
communicates this information with all concerned parties
in Maintenance and Operations et al.
Maintenance Supervisor – looks after the day-to-day
activities comprised in the weekly schedule. He assigns
his Technicians in a best-fit fashion to the various
Work Orders. He also determines the trade availability
for the week using a simple Excel Spreadsheet and
forwards that on to the Scheduler. (This spreadsheet can
be downloaded from
www.pop-ware.com)
Craftsman
– carries out the assigned work and communicates the
results as well as any discrepancies in planning or
scheduling of the work back to Maintenance for further
analysis.
Storeroom
Personnel – notify Maintenance of receipt of goods
and any deviation from the expected standards such as
damaged packaging. This affords Maintenance an
opportunity to job stage and inspect the material prior
to executing the work order and then finding out it is
damaged.
Operations Superintendent – must be informed well in
advance so that the equipment can be released to
Maintenance. This individual is aware of production
schedules and can determine the opportune time with
Maintenance to release the equipment.
Operator
– is the person responsible for securing the equipment
by performing the proper lockout and any block and bleed
requirements as well as any vessel entry preparations
such as purging and gas detection.
Short daily
scheduling meetings must be held to update the schedule
and communicate deviations from the schedule. Planning
and scheduling are crucial to maintenance management.
Being proactive as opposed to reactive cannot be
stressed enough.
Doc
Palmer, a noted authority in the area of Maintenance
Scheduling, cites six points that comprise good
scheduling principles.
1.
Job plans
providing number of persons required, lowest required
craft skill level, craft work hours per skill, and job
duration information are necessary for advanced
scheduling.
2.
Weekly and
daily schedules must be adhered to as closely as
possible.
-
Proper
priorities must be placed on new work orders to prevent
undue interruption of these schedules.
3.
A Scheduler
develops a one-week schedule for each crew based on
craft hours available, forecast that shows highest skill
available, job priorities, and information from the job
plans.
-
Consideration
is also made of multiple jobs on the same equipment or
system and of proactive and reactive work available
4.
The one-week
schedule assigns work for every available work hour. The
Schedule allows for emergencies and high priority,
reactive jobs by scheduling a significant amount of work
on easily interrupted tasks.
-
Preference is
given to completing higher priority work by
under-utilizing available skill levels over completing
lower priority work.
5.
The crew
supervisor develops a daily schedule one day in advance
using current job progress, the one-week schedule and
new high priority, reactive jobs as a guide. The crew
supervisor matches personnel skills and tasks.
-
The crew
supervisor handles the current day’s work and problem
even to rescheduling the entire crew for emergencies.
6.
Wrench time is
the primary measure of work force efficiency and of
planning and scheduling effectiveness.
-
Work that is
planned before assignment reduces unnecessary delays
during jobs and work that is scheduled reduces delays
between jobs.
-
Schedule compliance is the
measure of adherence to the one-week schedule and its
effectiveness.
Doc
Palmer: Maintenance Planning and Scheduling Handbook:
McGraw-Hill: New York: 1999 Page 3.2
Making It Work
The Area or
Crew Supervisor completes the Trade Availability
Spreadsheet and forwards it to the Scheduler.

Based on the
Available Hours to Schedule by Trade the Scheduler is
now able to schedule jobs that are “ready to schedule”.
The
Scheduler first Schedules all “due PMs” for the period.
Once that is complete he can view the remaining hours
available to Schedule Work Orders by Priority. Many EAM
and CMMS systems have the ability to track trade
availability and the remaining hours after Work Orders
have been scheduled and highlights in red where the
trade has been overbooked. The Crew Supervisor working
with the Scheduler is in the best position to make
decisions as to which trades are appropriate for each
PM. In some cases an Apprentice or Instrument Tech
could perform some of the Electrical PM’s. Similarly a
Mechanic or Apprentice could be assigned the Millwright
PM tasks.
Work Orders
by Priority are added until the EAM/CMMS system
indicates that the Trade Time has been fully utilized
for this particular Crew. Many CMMS/EAM systems provide
the option of exporting the Schedule to MS Project for
further manipulation. However, it is not necessary for
users to use MS Project to perform scheduling. The Crew
Supervisor can simply take the list of scheduled Work
Orders and simply assign the Work Orders to the
tradesmen on a daily basis.
Scheduling
cannot happen in a vacuum - it is imperative that
weekly scheduling meetings take place involving the
following individuals: Scheduler, Maintenance/Electrical
Supervisor(s), Operations Supervisor (or
representative), and Engineering. Communication between
these individuals in determining which Work Orders make
the schedule as well as the availability of the
equipment to be released to Maintenance is crucial.
Production runs and demands are vital; just ask a
marketing manager who has had to deal with an irate
customer as a result of a delivery being late because of
poor scheduling or worst – equipment breakdown!
Daily
scheduling meetings help plan for the upcoming day and
provide a means to review the events of the past 24
hours. This allows for any new “urgent” work orders to
be addressed. This meeting involves the following
individuals: Scheduler, Maintenance/Electrical
Supervisor(s), Operations Supervisor (or
representative), and Engineering. The communication that
takes place at this meeting allows first line
Supervisors to assign the work for the day and provides
Operations direction as to which equipment needs to be
released to Maintenance. Contingency plans are
formulated where equipment cannot be released.
Following
this meeting the Maintenance Supervisor can hand out the
Work Orders to the Crew for the day and post a daily
Schedule of the work that is taking place. Bear in mind
that maintenance technicians are not sitting idly by
waiting for work assignment from the morning meeting.
They will be performing PM Work Orders or working on
carry over work from the previous day.
The daily
Schedule provides collaborative information as to what
is happening or about to happen on the plant floor. It
helps formulate a big picture view of what’s happening
and the potential impact of each individual maintenance
technicians’ activities.
Conclusion
Many
organizations have tried to address their maintenance
scheduling woes by introducing new and sometimes very
advanced technologies. The reality is that trying to
automate something that’s broken will cause even more
frustration and finger-pointing. The potential
benefits of scheduling automation are best achieved by
first establishing a sound communication foundation that
supports scheduling business processes. By sticking to
these basics, most organizations can achieve significant
improvements in their maintenance scheduling
capabilities.
While
attaining 100% maintenance schedule compliance may seem
as difficult as pushing string uphill, it should still
remain an ultimate goal. It all starts by putting
together an effective PM program with cross-functional
communication – so everyone is in the loop. By moving
closer to this goal, organizations will become more
proactive in their approach to maintenance.
Lorne MacDonald has over 27 years experience in
maintenance and manufacturing in various roles including
contingency planning and scheduling, primarily for major
pulp and paper companies. During the past 6
1/2
years at PopWare, Lorne has been actively involved in
Enterprise Asset Management consulting engagements at a
number of large North American and European
manufacturers. For more information please visit
www.pop-ware.com
|