|
by Dave
McKinnon, Project Manager,
PdMA
For a
print friendly 136k pdf version click here
As motor
drives become more important in industry, the need to
analyze faults associated with them increases. PdMA’s
MCEmax is
a great tool for analyzing faults in Variable Frequency
Drives (VFDs).
Although
modern technology has seen great improvement in the
reliability of drives, naturally occurring events will
cause faults in a drive, especially if they were
originally installed in an inappropriate application.
The primary focus of this article is on Pulse Width
Modulated (PWM) drives without fault mode operating
capabilities. Although these drives do not employ fault
mode operation capability, in some cases, they will keep
running even with a fault. This article will show that
through the use of the MCEmax
technology, faults in these drives are detectable with a
very high level of confidence.
Fault Detection
As with
other predictive maintenance technologies, trending is
the best method of fault detection. Trending
methodology also applies to fault detection in VFDs. By
trending data over a period of time, a technician is
better able to detect developing problems in motors or
power systems. Occasionally, faults occur that did not
exhibit any trends before the occurrence, these types of
failures are considered random in nature. This article
covers faults that have occurred, yet, the drive
continues to operate in a mode that appears normal
externally.
Upstream (Line Side)
Diagnosis
Upstream
(Line Side) diagnosis of the VFD (not diagnosis of the
motor) refers to testing on the incoming power to the
VFD as shown in Figure 1. By testing upstream of the
VFD, open diodes and open phases can be detected using
the MCEmax.
Upstream diagnosis is only useful for diagnosing the VFD,
do not perform overall motor diagnostics upstream of the
VFD.

Figure 1
Open diode
Using the
MCEmax
technology, a technician is able to reliably detect an
open diode fault (Figure 2) using the results from a MCEmax
Power Test.

Figure 2
|
Table 1
|
|
Non-Faulted |
Faulted |
|
Current 1 (RMS) |
0.54 |
0.74 |
|
Current 2 (RMS) |
0.54 |
0.29 |
|
Current 3 (RMS) |
0.50 |
0.70 |
|
The phase
current (Current RMS) of the phase with the open
diode will decrease approximately 50% on the
affected phase, and increase slightly on the other
two phases (Table 1). |
|
Table 2
|
|
Non-Faulted |
Faulted |
|
% Current Imbalance |
4.79 % |
49.32 % |
|
Percent
(%) Current Imbalance will increase to approximately
50% on the affected phase (Table 2). |
|
Table 3
|
|
Non-Faulted |
Faulted |
|
Current 1 (THD) |
151.56 |
169.94 |
|
Current 2 (THD) |
148.84 |
79.19 |
|
Current 3 (THD) |
154.02 |
168.61 |
|
Current
THD will decrease by approximately 50% on the
affected phase, and increase slightly on the other
two phases (Table 3). |
|
Table 4
|
|
Non-Faulted |
Faulted |
|
Phase 1 kW |
0.06 |
0.09 |
|
Phase 2 kW |
0.06 |
0.03 |
|
Phase 3 kW |
0.06 |
0.08 |
|
kW will decrease by
approximately 50% on the affected phase, and
increase on the remaining phases (Table 4). |
|
Table 5
|
|
Non-Faulted |
Faulted |
|
Phase 1 kVAR |
0.11 |
0.16 |
|
Phase 2 kVAR |
0.11 |
0.09 |
|
Phase 3 kVAR |
0.11 |
0.15 |
|
kVAR
will decrease by approximately 20% on the affected
phase, and increase by approximately 40% on the
remaining phases (Table 5). |
|
Table 6
|
|
Non-Faulted |
Faulted |
|
Phase 1 kVA |
0.13 |
0.19 |
|
Phase 2 kVA |
0.13 |
0.10 |
|
Phase 3 kVA |
0.12 |
0.17 |
|
kVA
will decrease by approximately 20% on the affected
phase, and increase by approx 40% on the remaining
phases (Table 6). |
Of
these methods, the best method of detection is the RMS
current decrease of approximately 50% and the % Current
Imbalance increase to 50%, which is detectable for all
frequencies from 15 Hz to 60 Hz and loads from 0% Load
(no-load) to 100% Load. The next best detection method
is the current Total Harmonic Distortion (THD) decrease
of approximately 50%.
After
detecting a possible fault in the drive, you should try
to verify the fault is in the drive, and not a
measurement error. To do this, switch the test leads of
the MCEmax
between two of the phases, and perform the power test
again. If you receive the same results, except on a
different phase, the fault is most likely in the drive.
Shorted diode
A shorted
diode trips the drive on occurrence, therefore, there
are no detection procedures for this type of fault.
Open phase
An open
phase occurs when a connection has come loose either at
the component level or externally to the drive (Figure
3).

Figure 3
A technician
can detect an open phase by the following:
|
Table 7
|
|
Non-Faulted |
Faulted |
|
Current 1 (RMS) |
0.53 |
0.00 |
|
Current 2 (RMS) |
0.52 |
0.99 |
|
Current 3 (RMS) |
0.50 |
0.98 |
|
RMS current
on the faulted phase will decrease to 0.00 Amps and
increase on the other two phases by approximately
90% (Table 7). |
|
Table 8
|
|
Non-Faulted |
Faulted |
|
% Current Imbalance |
3.57 % |
99.62 % |
|
% Current
Imbalance increases to approximately 100% (Table 8). |
|
Table 9
|
|
Non-Faulted |
Faulted |
|
Current 1 CF |
3.51 |
15.41 |
|
Current 2 CF |
3.37 |
4.31 |
|
Current 3 CF |
3.66 |
4.31 |
|
Current
Crest Factor (CF) on the faulted phase increases to
approximately 15% and there is a slight increase on
the other phases (Table 9). |
|
Table 10
|
|
Non-Faulted |
Faulted |
|
Phase 1 kW |
0.06 |
0.00 |
|
Phase 2 kW |
0.06 |
0.09 |
|
Phase 3 kW |
0.06 |
0.11 |
|
Total kW |
0.19 |
0.20 |
|
kW
decreases to 0.00 on the faulted phase and increases
by approximately 50% on the other phases, but the
total kW remains constant (Table 10). |
|
Table 11
|
|
Non-Faulted |
Faulted |
|
Phase 1 kVAR |
0.11 |
0.00 |
|
Phase 2 kVAR |
0.11 |
0.26 |
|
Phase 3 kVAR |
0.11 |
0.25 |
|
Total kVAR |
0.32 |
0.51 |
|
kVAR decreases to 0.00
on the faulted phase and increases by approximately
100% on the other phases (Table 11). |
|
Table 12
|
|
Non-Faulted |
Faulted |
|
Phase 1 kVA |
0.12 |
0.00 |
|
Phase 2 kVA |
0.12 |
0.27 |
|
Phase 3 kVA |
0.12 |
0.27 |
|
Total kVA |
0.37 |
0.55 |
|
kVA
decreases to 0.00 on the faulted phase and increases
by approximately 100% on the other phases (Table
12). |
Downstream (Load
Side) Diagnosis
Downstream
fault diagnosis of the VFD refers to testing on the
output side of the VFD, which is between the VFD and the
motor as shown in Figure 4. By testing downstream of the
VFD, open diodes, and open phases can be detected using
the MCEmax.
Testing downstream of the VFD is not the preferred
location when performing VFD diagnostics (Line Side is
the preferred location), but is the recommended test
location when performing overall motor diagnostics.

Figure 4
Open diode
A technician
is able to detect a faulted diode in the rectifier
portion of the drive by using the MCEmax
technology downstream of the drive. At 60 Hz, with the
motor loaded to at least 50%, an open diode is
detectable by an increase in the Phase-Neutral Voltage
Imbalance to approximately 15% (Table 13).
Table 13
|
|
Non-Faulted |
Faulted |
|
Voltage Imbalance Ph-N |
0.42 % |
15.14 % |
Phase out
One phase
that was completely out (open connection) was reliably
detectable downstream of the drive when the drive was
operating at 60 Hz (at any load) by an increase in the
Voltage Imbalance to approximately 50%. At lower
speeds, a phase out fault was not reliably detectable.
Table 14
|
|
Non-Faulted |
Faulted |
|
Voltage Imbalance Ph-N |
1.11 % |
54.73 % |
After a Fault is
Detected
Once any of
these faults are detected, although the drive may still
be running, it is recommended that you repair or replace
the drive, or contact the manufacturer of the drive for
their recommendations. Failure to remedy the situation
may result in excessive heat in either the drive or the
motor and cause far greater losses.
Conclusions
From our
research, we found certain faults in drives can be
reliably detected using the MCEmax
technology (Table 13). These faults include an open
diode and an open phase. Open diodes were detectable
both up and downstream of the drive. An open phase was
detectable upstream of the drive at all frequencies and
loads. Furthermore, an open phase was detectable
downstream if the drive was running at full speed
(typically 60 Hz), but it was not reliably detectable
downstream if the drive frequency was below 60Hz.
Future research will include a line and load side
analysis of the back-end of a drive with back-end and
power circuit related anomalies, and other possible
detection methods using the MCEmax
technology.
Table 15
Fault
Detection Capabilities of the MCEmax
Technology
|
Component |
Type of Fault |
Detectable Upstream |
Detectable Downstream |
|
Diode |
Open |
Yes |
Yes * |
|
|
Short |
No (Drive
Failure) |
No (Drive
Failure) |
|
Phase |
Open |
Yes |
Yes * |
|
|
Short |
No (Drive
Failure) |
No (Drive
Failure) |
* when the
motor is run at full speed (typically 60 Hz).
Related
Sources
Bezesky,
David M., Kreitzer, Scott, “NEMA Application Guide for
AC Adjustable Speed Drive Systems,” IEEE/PCIC 2001
Conference 7, 9.
Braun, D.,
Pixler, D., LeMay, P., “IGBT Module Rupture
Categorization and Testing,” IEEE Industry
Applications Society Annual Meeting, (October 1997).
Budek,
Roman. “Troubleshooting IGBT Failures,” IXYS
Application Note #11 Martan, Inc., (Last Revised
8/21/02).
Houdek, John
A., “Reactors Maximize Drive System Reliability,”
Power Quality Assurance, (February, 2000).
Mayfield,
Eddie, “Troubleshooting Variable Speed AC Motor Drives,”
http://www.maintenanceresources.com/ReferenceLibrary/ACDrives/drive.htm
(January 26, 2004).
Mendes, A.
M. S., and Cardoso, A. J. Marques, “Performance Analysis
of Three-Phase Induction Motor Drives Under Inverter
Fault Conditions,” SDEMPED 2003, (August 2003).
Welchko,
Brian A., Lipo, Thomas A., Jahns, Thomas M., and Schulz,
Steven E., “Fault Tolerant Three-Phase AC Motor Drive
Topologies; A Comparison of Features, Cost, and
Limitations,” IEEE-International Electrical Machines and
Drives Conference, June 1-4, 2003. IEEE Catalog Number
03EX679C, ISBN 0-7803-7818-0.
|