|
Web-based
connection to Equipment Reliability (ER)
To ensure reliable and efficient equipment operation
there are many tasks that need to be performed
effectively. These tasks cover the range from
significant to small and each one has equal importance
because any break in the chain, however small, reduces
or eliminates the beneficial outcome. It is recognized
that performing some of these tasks can be extremely
difficult, and in some cases impossible, unless there is
some automation applied.
By Bob
Hammaker, Insert Key
Solutions, Inc
Fifteen
years ago condition monitoring was becoming more widely
used resulting in less breakdown maintenance and
run-to-failure practices on critical equipment. Advanced
diagnostic tools, data integration, and newly developed
processes were starting to change the way maintenance
was being performed. This new maintenance strategy was
commonly referred to as Predictive Maintenance (PdM).
PdM is an approach that determines the need for
equipment being repaired or replaced based on the
condition of the equipment. The goal during this time
was to not only perform PdM, but to also have the
appropriate mix of PdM and Preventative Maintenance (PM)
activities to reduce Corrective Maintenance (CM), which
results in unscheduled downtime, prevents costly
repairs, and increases equipment reliability.
As time
went on, new technologies were developed, improved data
collection techniques were discovered; and, most
importantly, it was realized that data collection was
only as good as the end results. There needed to be a
better process to convert data to information, and then
to take action. No matter how effective technology
owners were at diagnosing an equipment’s condition,
unless it was being applied to the right equipment,
using the right technologies, at the right frequencies,
integrating the data with other plant information (i.e.,
process, historical, etc.), and the findings acted on at
the right time, it became very costly with little or no
benefits.
One area
identified as needing improvement was how to better
define the overall health of equipment using all of the
plant data. Generally, when a Technology Owner finds
equipment in an unacceptable condition, the Technology
Owner would write a Work Order for the equipment to be
repaired. Additional information that could assist in
better defining the condition such as system, process,
historical, and even other diagnostic technology data,
was not being used effectively, if at all; and, in most
cases, it was available. Technology Owner effectiveness
of using diagnostic tools varied by the Owner’s
background and few were well rounded in diagnostic
technologies, maintenance procedures, and operation of
the equipment. In order to ensure that all of the
available data was being used, it was decided to assign
a second person responsible to assess the overall
equipment condition that had the equipment and/or system
experience. In most cases they were referred to as
Equipment or System Owners. An Equipment Owner is a
person knowledgeable on certain types of equipment such
as motors, pumps, etc.; and, the System Owner, also
referred to as a System Engineer, is a person with
system knowledge of both Operations and Maintenance. In
general, a plant organization would have one or the
other. If the plant had both, they would assign only one
person to perform the assessment
responsibilities.
Determining the overall condition of equipment was now
becoming the responsibility of the Equipment or System
Owners. For example, an Infrared Technology Owner finds
a piece of equipment with an unacceptable temperature.
The Infrared Technology Owner analyzes the temperature
data to determine the condition of the equipment based
on this technology and these findings. The information
is then provided to the Equipment or System Owner to
apply the knowledge about the equipment or system. Any
additional data needed from other technologies or
sources is the responsibility of the Equipment or System
Owners to initiate.
Initially,
equipment conditions were tracked using software
products such as Microsoft ExcelTM. The
software was located on the plants ‘common’ drive so
that it was accessible to all plant personnel. The
report generated was referred to as the Condition Status
Report. Generally, the equipment’s condition was
represented using colors such as: Acceptable (green);
Watch List (blue), meaning the equipment does not
require repairs but will most likely be monitored more
frequently; Marginal (yellow), requires a Work Order for
repairs and should be expected within a specified period
of time; and, Unacceptable (red), meaning there is an
imminent failure possible, and immediate action is
required.
Figure 1
shows graphically how this color-coding can be developed
to demonstrate the condition of various pieces of
equipment, and how the responsibilities of the
Technology Owner, Equipment Owner, or the System Owner,
ties in with the equipment selected. Each Technology
Owner is responsible for diagnosing the condition of the
equipment based on his or her respective technology;
therefore, that person fills in the chart vertically for
that particular technology. The responsible Equipment or
System Owner can then determine the condition status of
each particular piece of equipment by scanning the chart
horizontally, and then completing the ‘overall equipment
condition’ column.

The
process of converting data to information was now being
improved with the Technology, Equipment, and Systems
Owners; however, it was noted in Figure 1 that the
data-to-information activities are being performed on
the most ‘critical’ plant equipment. An initial analysis
process, therefore, was needed to identify the critical
equipment and to define a protection strategy for each
of these vital pieces. One of the first analysis
programs to accomplish this task, referred to as
Reliability Centered Maintenance (RCM), provided a very
thorough review of the design of each system, the
system’s equipment, and the failure modes, to formulate
a maintenance strategy that provides safe, efficient,
and cost-effective operation. The maintenance strategy
not only identifies the right mix of PM, PdM, and
corrective maintenance (CM), it also includes Proactive
Maintenance (PAM). PAM is actually a process within
itself that identifies equipment design problems, and
this approach is discussed in more detail later.
Additional
analysis methods followed RCM providing similar results
and they include: Maintenance Basis Optimization (MBO);
PM Strategy; and PM Basis Strategy, to name a few. Each
of these analysis methods provides the user with an
enhanced PM strategy that defines the critical
equipment, condition monitoring activities, and the
frequency of the equipment monitoring activities
required to maintain efficient and effective operation.
The specific maintenance tasks being performed in Figure
1 are dictated by the PM Strategy study. An example of
the type of information that would be provided as a
result of a PM Strategy study is depicted in spreadsheet
form in Figure 2. In this chart, the equipment condition
status color-coding in Figure 1, for the Periodic
Monitoring activities, is replaced by monitoring
frequency codes.

Generally,
results of the PM Strategy that require physical data
collection or routine maintenance activities are entered
into the Computerized Maintenance Management System
(CMMS) for dispatching work in the form of a Work Order.
The PM Strategy should be treated as a controlled
document such that any changes requested are
appropriately reviewed and documented. The approved
changes are then made to the PM Strategy document, and
to any other supporting documentation such as the CMMS.
Planning
and scheduling of work activities have also evolved
immensely over the past several years. Businesses have
gone from the ‘fix it when it fails’ reactive mode to
the well-planned ‘fix it before it fails’ mode. Much of
the latter ‘fix it before it fails’ approach can be
attributed to the advancements in diagnostic
technologies and a more developed work process. Planning
and scheduling activities vary greatly. Personnel, from
the maintenance craft to established planners and/or
schedulers have successfully performed planning and
scheduling activities. However, many times these
activities are done with little input from other
disciplines within the organization; thus, critical
information could be lost that could better define what
equipment should be worked on now, based on the
equipment’s condition and its criticality to the
operation. Changes to this process have evolved to
include not only how a planner and a scheduler supports
the process, but also who needs to be involved to
capture the appropriate information to make an effective
decision. One enhanced process, referred to as the ‘Work
Process’, links Work Control, Work Execution, and Work
Closeout, as illustrated in the Figure 3.

Work
Control is a formalized planning and scheduling process.
Planning involves making the right job ready to be
worked, and scheduling ensures that the planned work is
performed when needed. These tasks seem basic but there
are many activities that, if not performed effectively,
can result in someone being assigned to a job that is
not ready to be worked; or, a low priority job being
worked rather than a job, that if not repaired, could
cause additional equipment damage and possible failure.
A well-planned job is the assembly of the necessary
information, which should include: job scope; applicable
procedures; time estimates; parts availability; permit
and blocking instructions; and, special tools, just to
name a few. The assembly of information is often
referred to as a ‘Work Package’. After the Work Package
is complete, then the Scheduler can assign the
appropriate time for the work to be performed as
dictated by the criticality, resources, and availability
of the equipment to be worked.
Work
Execution is the act of carrying out the Work Order
instructions, and providing feedback on all of the
activities. This includes the wrench-turning work, as
well as other directions such as notifying that a Post
Maintenance Test (PMT) should be performed. Feedback
also includes any comments as needed on the repair,
parts, procedure quality, as-found / as-left
information, etc. Generally, the diagnostic Technology
Owner provides the PMT to ensure that the repairs were
done effectively, and to capture baseline data for
future comparative diagnoses.
Work
Closeout is a process that involves documenting the
notes provided by the maintenance personnel. The
information, if properly captured and documented, can be
used to enhance any of the other processes. For example,
little or no damage found on a component during repair
would throw up the red flag that the severity criteria
being used by the Technology Owner needs to be adjusted;
or, that the same problem that has been occurring every
three months would indicate that a design, maintenance
or operating change is needed.
As the PM
Strategy, Work Identification, and Work Control
processes continued to evolve, companies that
implemented these processes were still experiencing some
undesirable equipment conditions and failures. Defining
a facility’s maintenance strategy, making the
appropriate equipment condition decisions with new
technologies and applications, working on the right
equipment at the right time, and communicating
appropriately throughout the entire process are a
challenge to say the least. Improvement processes were
added to the existing list of activities, two of these
being Pro-Active Maintenance (PAM) and Continuous
Improvement.
PAM is a
process that identifies various unexpected equipment
conditions that result in repetitive problems, costly
repairs, and failures. PAM utilizes ‘as found’
conditions and unexpected failures to identify the need
for an adjustment to the existing practice or equipment
design. PAM results in an adjustment to the operation,
maintenance, and/or the replacement or modification of
equipment based on a root cause analysis (RCA). RCA is a
process that identifies the most basic cause of the
problem and, when corrected, minimizes or eliminates the
reoccurrence of the problem.
Continuous
Improvement is similar to PAM and in some publications
the terms are interchangeable. It is a process that
provides the review, analysis, and recommended changes
to any of the other processes. Considerations include:
technology program review and adjustments; review of
Work Orders (good and bad); and, monitoring metrics
around PM, PdM, and Work Control, to name a few. Results
are used to enhance the process and to reduce functional
failures and/or maintenance costs. Metrics are the
indicators that are trended to measure the success of
the process (i.e., safety, reliability, availability,
financial, etc.).
PM
Strategy, Work Identification, Work Control, and
Continuous Improvement when combined are considered the
Equipment Reliability (ER) Process. ER supports the how,
what, and when equipment is maintained and operated for
optimum performance and reliability. The ER process is
not difficult to understand; however, there are a great
deal of functions that require support; and, unless the
process is automated it is difficult to implement and
maintain. Figure 4 provides the many of the activities,
but is not limited to, for each of the ‘sub-processes’
that make up the Equipment Reliability Process.

Implementation of the ER process can be approached
several ways. Being that each sub-process (i.e., PM
Strategy, Work Identification, Work Control, and
Continuous Improvement) can provide benefits
individually, it may be that the Enterprise’s available
resources limit the approach. If an Enterprise does not
have enough resources to conduct all of the
sub-processes simultaneously, then it should initially
select the area that would provide the most payback,
implement that process effectively, and then go to the
next needed area when time and resources permit.
Since
there are many businesses that currently do not provide
the
tools and training to support the ER process, it is
important that they explore the benefits and have a good
understanding of the ER process and the resources that
are required for proper implementation and continued
program support. The ER process is a culture change. It
is how we are going to do business now and in the
future. Automation standardizes each of the areas that
make up the ER Process, provides metrics to monitor the
process status, identifies where the process chain is
broken, supports accountability, and provides a
means to better facilitate communication. Automation;
therefore, is the vehicle that connects the
sub-processes together so that ER can function as a
single process and thereby provide the most beneficial
results.
|
There are many software programs on the market that
can help automate the ER process. However, it
becomes a serious search effort to find the ones
that are best suited to a particular industry or
plant. Insert key
Solutions, Inc. has developed several such
programs for the Electric Power Industry, and these
programs are currently being modified to other
industries. Electric Power Generation plants have a
range of equipment and systems that far exceed most
plants (Turbines, Generators, Pumps, Motors, Heat
Exchangers, Feedwater Heaters, etc.) In addition,
Nuclear plants have Reactors, and Fossil plants have
coal handling and crushing equipment and, in many
cases, oil and natural gas supply systems. The Power
plant requirements, therefore, have been very
demanding; but, ER automation systems have been
successfully applied and have produced substantial
results and, as a result, automation systems are
being added to additional plants every day.
|
|