INTRODUCTION
This paper
presents the turning around of a
mechanical maintenance planning department
within a large municipal electric utility. It
explains how planning leverages maintenance
productivity and how its effect is quantified.
The specific
principles necessary to make
planning and scheduling effective are
presented and the issues underlying each
principle are identified.
The utility
had a multi-faceted maintenance
management improvement effort to insure
continued maintenance effectiveness. This
effort comprised areas such as
communication and teamwork, storerooms,
rotating spares, tools, tool rooms, shop
improvements, training at all levels,
equipment database and CMMS, PM, PdM,
project work, and improvements to work
processes. Many of these areas were mature
and already contributing to the utility
success. The most recent area to come into
its own was planning and scheduling.
COMPANY VISION
AND PLANNING
MISSION
Of course in
one respect, a company should
not want to do maintenance. Gifford
Brown, Manager, Cleveland Engine Plants,
Ford Motor Company, says it best:
"The company
vision should be how
to PREVENT maintenance, NOT how
to do it efficiently."2
However,
knowing that some maintenance is
necessary, the utility counts work order
planning as an important tool. Some of the
primary aspects of planning are well known.
Work order
planning involves identifying
parts and tools necessary for jobs and
reserving or even staging them as
appropriate. As more was learned about
planning, it became apparent that planning
was also a system with many subtleties.
"Having the
right jobs ready to go" sums up
the planning mission statement. Having the
"right jobs" involves job priorities, crew
schedules, and work type (such as PM
versus breakdown work). Having the jobs
"ready to go" involves correctly identifying
the work scope, considering the safety
aspects of the job, and planning to reduce
anticipated delays such as for instructions,
parts, tools, clearances, and other
arrangements.
The practical
result of planning for the
mechanical maintenance department where
planning was implemented was 30
maintenance persons yielding the effect of
47 persons.
At this point,
it must be stated that the
benefits of planning involve quality as well
as productivity. It is very dangerous to
push for productivity if there is not a
quality focus present in the work place.
Craft persons
must have the attitude that
work being done in a quality fashion is more
important than meeting a production
schedule. The individual on the floor must
communicate concerns with the crew
supervisor if more time is needed to
complete work properly. Tangible quality
savings come from improved availability,
heat-rate, and safety in two ways. First,
planning focuses on correctly identifying
work scopes and provides for proper
instructions, tools and parts being used
thereby facilitating quality work. Second,
productivity improvement frees up craft,
supervision, and management time to do
more proactive work. This proactive work
includes root cause analyses on repair jobs,
project work to improve less reliable
equipment, and attention to preventive
maintenance and predictive maintenance.
The reduction
of delays is where planning
impacts productivity. The majority of the
maintenance budget is typically wages and
benefits. Studies during the last four years
in spite of high availability indicated that
productivity of available maintenance
persons was about 35%. That is, on the
average, a typical maintenance person on a
10 hour shift was only making productive
job progress for 3 1/2 hours. The other 6 1/2
hours were spent on "non-productive"
activities such as necessary break time or
undesirable job delays to get parts,
instructions, or tools. 30 to 35%
productivity was typical of traditional-type
maintenance organizations. Yet it was clear
that the significant overall cost of
maintenance and the average of 6 1/2 hours
"non-productive" time per person were
opportunities to improve maintenance
efficiency. Simply implementing a
fundamental planning and scheduling system
should help improve productivity from the
30-35% of a traditional type maintenance
organization to about 45%. Then as files
become developed to allow avoiding the
problems of past jobs, productivity should
increase to 50%. Finally, having other
mature facets of maintenance such as a good
storeroom, trained technicians, engaged
supervision, and perhaps a good CMMS might
even boost productivity to near 55%.
Taking
technicians out of the work force to
make them planners makes sense because a
single planner can plan for 20 to 30 persons.
This ratio is
well above the break-even
point. If a planner could help multiply the
productivity of a single technician by 57%
(55% divided by 35%), the break-even point
would be taking one of every three
technicians and converting them to planners:
Without
Planner:
3 persons at
35% each = 3 X 35%
= 105% total
productivity.
With Planner:
2 persons at
55% and 1 planner at 0%
= (2 X 55%) +
(1 X 0%)
= 110% total
productivity.
The 30 person
maintenance force is
leveraged as 30 persons X 1.57 to yield a 47
person effective work force.
THE SIX
PRINCIPLES OF PLANNING
It soon
appeared there were six principles
necessary to make planning effective. They
are discussed as follows:
Principle #1
The first
principle is to have a separate
department. There is frequently significant
pressure on the maintenance supervisor to
get repairs completed. It is tempting to
reassign a planner to a toolbox, saying, "One
of those planners is a welder, he can come
help us." This situation is avoided by
removing the planners from direct control of
the maintenance crew. The reason they need
to be separate is they need to focus on
future work.
Principle #2
A simple
definition of future work is: the
crew has not yet been assigned to start on
the work order. Once a crew has started
working on a job and they find out they need
more parts information, they do not come to
the planner for assistance. If the planner is
constantly helping technicians find file
information for jobs-in-progress, the planner
has no time to file or retrieve job information
to help future work and a vicious cycle is in
place. A planner must be able to find those
last three work orders from the last four
years to help the crew avoid previous
problems. For example, if the planner finds
that the last time the crew worked this job
they did not have a certain part, the planner
makes sure they have that part this time.
So the job is
on a learning curve. Looking to the
files helps get that improvement
opportunity. And that lets the planner
focus on getting all of the work planned in
advance. In addition, if a planner can
tabulate the previous cost, better repair or
replace decisions can be made. This
arrangement is also necessary for the crew
supervisors to maintain their familiarity with
the files and encourages feedback from the
technicians. Once a technician has to find
technical information for a job, feedback to
the files is encouraged if he knows that
otherwise, the next time he works the job he
will have to find the information again
himself.
Principle #3
Once the
planner gets job feedback for future
reference, it cannot go into a system level
file. A system might have 20 to 100
components with many work orders. When
a file is that large, information cannot easily
be found on a single piece of equipment. So
planners use a component level file for each
piece of equipment. When a work order is
received, the planner consults the specific
file to find the previous work orders for that
equipment. These component files used
were simple paper files.
Principle #4
It would seem
that with the feedback and file
system in place, clerks might be utilized as
planners. However, as a minimum, planners
need to be skilled technicians so that they
can intelligently scope a job or inspect the
information in a file for its applicability to
the current job being planned. One issue at
stake is in whether to have (hopefully) good
execution on an excellent job scope or have
excellent execution of perhaps the wrong job
scope. Identifying the correct job scope is
of primary importance. Another issue is the
development of time estimates. The opinion
of the skilled technician-planner is preferred
over strict file information, pigeon holing,
and other built up time estimates. The
planner estimates how long it should take a good
technician without unanticipated
delays. Planners must also have a high
degree of self-initiative.
Principle #5
Planners have
to be careful not to put so
much detail in a plan that they cannot plan
all the work. A general strategy for 80% of
the work hours is better than a detailed plan
for only 20%. Therefore the planners must
respect the skill of the craft. Supervisors
must shore up technicians with deficient
skills rather than the planners planning jobs
for a lower skill level. In the past, the
planners had not only wasted time planning
unnecessary details, but had affronted skilled
technicians. On the other hand, if there is a
procedure already in the file or if the persons
who previously worked on the equipment
reported helpful feedback, the planner would
include those items in the package. The
planner should also include information as to
why the certain job strategy was chosen,
especially when the file history helped make
the decision. For example, "This valve is
being replaced since patching it in the past
has not worked well" (the planner knows the
file history). The planners want to develop
detailed procedures over time, not
necessarily perfect them for the current job.
Principle #6
Finally, work
sampling (also known as
wrench time) gives the measure of whether
planning is helping. At issue is not so much
the time the technician spends doing
productive work. What is truly important is
the analysis of the non-productive time. For
example, how much time is spent waiting for
parts? Wrench time is properly measured
with a statistical study. Separate studies
done over time indicate if planning is getting
better or worse.
SCHEDULING
After the
utility had incorporated these
principles into its system, a work sampling
study was done. Comparisons to earlier
studies indicated that some delay areas had
been reduced. But it appeared that overall
productive time did not increase because
more work had not been assigned. Advance
scheduling was considered necessary for
improvement.
The basics of
scheduling revolve around
giving enough work to the crews to fill up
the crews' forecasts of work hours available.
Again, there
were six principles necessary to
make scheduling effective in getting more
work completed. They are discussed as
follows:
Schedule
Principle #1
The essential
part of principle #1 is that
plans identify the lowest skill necessary to
complete the work. By identifying the
lowest skill necessary, the crew supervisor
has more latitude later when determining
which individuals could execute each job
plan.
Schedule
Principle #2
The importance
of schedules and job
priorities cannot be presumed. Advance
scheduling enough work for an entire week
sets goals for maximum utilization of
available craft hours. It helps insure that a
sufficient amount of work is assigned. So,
while planning reduces delays during jobs,
scheduling reduces delays between jobs.
Advance
scheduling also helps insure that
sufficient proactive work to prevent
breakdowns is scheduled along with reactive work.
It also allows more time to coordinate
resources for completing work such as
inter-craft notification and staging of parts. If
there is inadequate confidence that scheduled
jobs would be executed then one of
two adverse
situations could occur. The first is
that no one would stage any parts and the
second is that the staging area would be
overflowing with staged parts for jobs that
are not going to be executed. In either case,
the great potential for staged parts to
expedite jobs is negated. Similarly, if
everyone assigned a high priority to "their"
work just to insure its completion, then
improperly prioritized jobs would delay true
high priority jobs (say directly affecting
plant availability). They would also make it
hard to recognize true instances of when the
advance schedule should be interrupted.
Schedule
Principle #3
The actual
schedule is a one week schedule
made from a forecast of the highest skills
available. From knowing the highest skills
available, the scheduler has more latitude
when determining which job plans could be
executed the next week. Another point is
that "advance scheduling" is really more of
an "allocation" of work to be done and not a
detailed "schedule" of exact individuals and
time slots.
Schedule
Principle #4
Principle #4
brings the previous schedule
principles together. The first part of this
principle is that the scheduler assigns work
plans to be executed during the following
week for 100% of the forecasted hours.
Over-assigning
and under-assigning work
each cause unique problems that can be
avoided. For example, assigning work for
120% of forecasted work hours may seem
to be a way
to provide enough work for the
crew in case some of their jobs could not be
cleared. It would also seem to encourage the
crew to stay busy. But it then
becomes
difficult to gauge the performance of a crew
when trying to compare what they did
accomplish to what they should have been
able to do. It certainly lacks a motivating
appeal to ask why a crew only accomplished
110 hours worth of work with the 100 work
hours it had available. Also coordination
with plant operators and other crafts may be
more difficult if there is less confidence that
equipment will be worked on. In the other
situation, assigning work for only 80% of
forecasted work hours may seem to be the
way to handle "emergencies or high priority
work that may come up." In this case it is
also difficult to gauge performance and it
would be difficult to ask a crew to improve
if it did "all of its assigned work." In reality,
assigning work hours for 100% of forecasted
work hours nearly always inherently
includes some jobs that can be easily
interrupted in case emergencies arise.
The second
part of this principle is more
subtle. On a major construction project
requiring 20 welders and 20 helpers, the
project would simply hire 20 welders and 20
helpers. However, in normal maintenance, the
higher priority jobs requiring completion
rarely match the skill composition of the
standing maintenance force. As a simple
illustration, consider a planned backlog
consisting of 20 hours of high priority work
requiring only helpers and 20 hours of low
priority work requiring welders. If there
were only 20 hours of welders available,
then they should all be assigned to the high
priority work even though it requires only
helpers. The principle is to have the system set
up to recognize that welders can do
helper work and allow assignment to the
highest priority work in the plant.
Otherwise,
think of a not-so-extreme case
where there was no welder work in the
backlog and welders could not "work down."
Would you have high priority helper work
sitting in the backlog and welders sitting in
the break room? Consider what type of
multi-craft or work agreements are necessary
to take advantage of the opportunities in this
area.
Schedule
Principle #5
Once the week
has begun, obviously some
jobs will run over and some will run under
their planned work hours. That is one
reason that daily scheduling is best done by
the crew leader who is close to the field
situation of job progress. Equally important
is the ability of the crew supervisor to assign
particular jobs to individuals based on their
experience or even their need to learn.
Schedule
Principle #6
Finally, while
wrench time is the best
measure of scheduling performance, schedule
compliance is also tracked. Measure
schedule compliance in a way to give the
crew the benefit of any doubt. Consider a
crew given 10 jobs and the crew started all
10, but only completed 9. We would give
the crew 100% schedule compliance rather
than 90%. Otherwise, in a second case
where a crew received only 1 job and worked
it all week without interruption, but did not
finish, we would be reluctant to grade them
as 0% schedule compliance. Again, we
would count them as 100% schedule
compliance. In actual practice, the situation
is as follows: We track the work hours
delivered to the crew for the following
week's work (say 1000 work hours). Then
at the end of the week the crew returns all
work they did not start (say 100 work
hours). The schedule compliance is very
easy to measure: (1000 - 100)/1000 times
100% = 90%. (That the crew may have
only actually completed 850 work hours is
not a problem as long as overall forecast
claims for available and carryover hours the
next week are monitored.)
PROACTIVE WORK
The last
barrier to having an effective system
was removed with the recognition of the
existing maintenance culture. John E. Day,
Jr. PE, Manager at Alumax of South Carolina
has done excellent work dealing with this
factor. He points out that the standard
definitions of maintenance are along these
lines:
Repair To
RESTORE by replacing a
part or putting together what
is torn or broken: FIX,
REJUVENATE, etc.
Maintenance
The act of maintaining. To
keep in an existing state:
PRESERVE from failure or
decline, PROTECT, etc.
He explains
"The key paradigm is that the
maintenance PRODUCT is CAPACITY.
Maintenance
does NOT produce a service."3
Initial
disenchantment in implementing the
planning system was primarily due to an
attempt to provide detailed work plans on
reactive jobs. Since reactive jobs by their
nature are urgent, it is frustrating to
everyone to wait on a planning group to turn over
the work. And planners were having
difficulty planning all the work. Planning
became successful when it reduced research
on reactive work. Reactive work still
received planning before crew assignment,
but the planners began to rely more on the
technicians in the field researching a job if
there was no file information. Not only did
this methodology allow all the work to be
planned to allow scheduling, but it reinforced
planning principle #2 for feedback.
The challenge
is to continue planning and
scheduling proactive work while a significant
amount of reactive work orders is still being
written. The utility is now further
developing its PM program to have a three
week backlog of work with equipment not
breaking.
RESULTS
The start of
weekly scheduling began in the
middle of May. The amount of work orders
being completed for mechanical maintenance
went from about 150 per month to over 250
per month in June and July. So much work
was done that even in mid-June there started
to be insufficient backlog to schedule for the
entire amount of work hours available for
each crew. The reason was that the crews
had worked down their entire outstanding
backlogs. These backlogs had even included
some work orders that were over several
years old. With the units caught up in
backlog, personnel were available to assist
other stations. The utility was also able to
proceed into its fall major overhaul of a large
steam unit successfully without contract
labor.
ONGOING
Emerging from
the overhaul of the unit, the
utility included the electrical and I&C crafts
(except for the controls maintenance) as well
as its other stations into the planning
system. The total of the maintenance force
at that point was 137 persons. With a 57%
productivity improvement from planning
and scheduling assistance, the utility
expected to free up in effect 78 technicians.
1. EAF is a
common utility performance measure of how
much generating capacity is actually
available over a given period for producing
power.
2. Society for
Maintenance and Reliability Professionals
Annual Conference, October, 1993.
3. Society for
Maintenance and Reliability Professionals
Annual Conference, October, 1993.