|
Incorporating Reliability Centered Maintenance Principles in Front End
Engineering and Design of Deep Water Capital Projects by Mack Morris,
Advanced Reliability
Technologies, LLC. Houston, Texas
This paper was originally delivered at the
Reliability Centered
Maintenance
Managers' Forum
Front End Engineering and Design comprises a logical progression from capital
project selection through capital asset commissioning and operation. Project
owners contract with engineering firms to provide capital project assessment,
design, equipment selection, procurement and start-up. During each phase of
Front End Engineering Design, (FEED) sound engineering judgment and industry
“best practices” are applied to improve Capital Expenditures (CAPEX) and
Operating Expense, (OPEX).
Within the
Gulf of Mexico (GoM) energy companies are heavily investing in the development
of GoM offshore oil fields in water depths of 7,000 feet or more. Recent
exploratory drilling has produced discoveries of oil and gas of commercial
volumes in water depths of 10,000 feet.
Energy
companies are confronting environmental and technological challenges never seen
before. Companies are investing billions of dollars in capital to develop subsea-producing
fields including the design and construction of offshore production platforms
capable of processing and delivering 50,000 to 250,000 barrels of oil per day to
pipelines reaching onshore refineries.
Not only do
the energy companies face the challenges of a new operating frontier with
billions of dollars in capital investment but energy companies also face the
challenges of complying with federal safety/environmental regulations. Operating
billion dollar investments in the Deep Waters of the Gulf of Mexico necessitates
utilization of new technology, improvement of asset reliability and reducing
operating expenses to ensure shareholder returns are met.
Deep Water
Operators in the Gulf of Mexico continue to improve CAPEX using “Best
Engineering Practices” in conjunction with, federal regulatory
requirements/codes and state-of-the-art technologies.
However,
further enhancements in CAPEX, asset reliability and reduced OPEX can be
achieved utilizing the principles of Reliability Centered Maintenance (RCM) in
the Front End Engineering and Design of Capital Projects.
This paper
focuses on a methodical process to incorporate the principles of Reliability
Centered Maintenance (RCM) into Front End Engineering and Design of Deep Water
Capital Projects to further improve reliability of system design, and reduced
OPEX.
Introduction
Market
demands, safety, environmental regulations, flow assurance and operating costs
pose significant challenges to all Deep Water operators. These challenges
necessitate improved asset reliability and reduced Operating Expenditures (OPEX).
Engineering organizations have improved CAPEX, equipment reliability and OPEX
utilizing “Best Engineering Design Practices.”
Best
Engineering Practices include but are not limited to federal regulations, codes
and general design practices such as American Petroleum Institute, Minerals
Management Service, United States Coast Guard, and American Bureau of Shipping.
Another “Best
Engineering Design Practice,” Reliability and Maintainability analysis (RAM) is
conducted during the early stages of project design. RAM is a statistical
analysis, which quantifies system reliability, availability and maintainability.
RAM analysis utilizes failure information from system components in order to
develop failure probability distributions. The analysis provides significant
design insights particularly the identification of primary contributors to
system unreliability. The results can lead the engineering firm to consider an
alternative design if the primary design fails to meet the expected project
deliverables.
A RAM
analysis encompasses sub sea production equipment, control systems and platform
topsides production systems. Failure data utilized in the analysis is resultant
from Offshore Reliability Data (OREDA) and it’s nine participants from six
different countries. Additionally, proprietary data from engineering firms
conducting the RAM analysis and internal failure data of the operating company
is utilized. The deliverables of the RAM analysis identifies critical events,
which contribute to system unavailability. Additionally the analysis provides
assistance in determining operational and maintenance strategies, life cycle
cost, including equipment operating spares, repair strategies and logistical
requirement considerations. However, combining the efforts of RAM in conjunction
with the principles of RCM will further enhance system reliability and reduce
OPEX.
Reliability
Centered Maintenance
Reliability
Centered Maintenance (RCM) methodology was developed by the airline industry in
the mid-1960’s to identify the necessary maintenance requirements for new fleets
of 747 and DC10 jet aircraft.
Since the
inception of Reliability Centered Maintenance, many industry sectors such as
energy, refining, chemical and manufacturing companies have adopted and
aggressively applied the principles of Reliability Centered Maintenance.
The basic
methodology of RCM is to first, determine equipment or component criticality
within a functional system. This is accomplished by identifying equipment
failure modes and analyzing the effects of failure resulting from each of those
modes. Secondly, to identify the causes of failure for each one of the
previously identified failure modes; and third, select the appropriate
preventive and predictive maintenance tasks including time-based and renewal
tasks), that specifically address the identified failure causes.
RCM is
conducted according to a set of principles. These principles are based on
probabilities. In fact, some industries, such as the airline and nuclear
sectors, have meticulously kept failure data for all types of components, and
can predict the mean times between failures (MTBF) for these components with a
high degree of accuracy. There are several benefits from the collection of
failure data. One of them is the ability to determine spare parts requirements.

As stated above, RCM is based on probability and risk management. Risk can be
expressed in the equation:
R=PxC
Where:
R=Risk
P=Probability
C=Consequence of Failure
Reliability Centered Design Analysis Benefits
Reliability Centered Design Analysis (RCDA) leverages the guiding principles
and rules that comprise the RCM methodology. Like RCM, RCDA is a formalized
methodology, following a step-by-step process, which lowers the probability and
consequence of failure, resulting in the most reliable, safe and environmentally
compliant design.
Direct
benefits using Reliability Centered Design Analysis in Front End Engineering and
Design are:
• Higher
Mechanical Availability, which results in longer operating intervals between
major outages for maintenance, significantly increasing revenue.
• Reduced
risk. RCDA results in designs that lower the probability and consequence of
failure.
• RCDA is a
functionally based analysis. It focuses on maximizing the reliability of
critical components required to sustain the primary functions for a process.
• Shorter
maintenance outages (turnarounds). Reduced downtime results in fewer days of
lost production, significantly increasing revenue,
• Safer, more
reliable operations, better quality control, more stable operation with the
ability to respond to transient process upsets.
• Lower
operating expense (OPEX). RCDA results in designs that cost less to maintain
over the operating life of the asset.
• Optimized
Preventive and Predictive Maintenance Programs and practices. A comprehensive
program is created during RCDA. Training to these practices are performed in
advance, so assets are maintained from the minute the project is commissioned.
• Emphasis on
condition-based maintenance practices. Equipment condition is continuously
monitored, maximizing the full potential of the assets, and avoiding unnecessary
inspections and costly overhauls.
• RCDA can be
used as a training tool for Operators and Maintenance personnel. RCDA documents
the primary modes of failure, their consequences and causes for failure well in
advance of building the platform.
•Spare parts
optimization. Because the dominant failure causes are identified for each piece
of equipment, the spare parts requirements are also known. Since this analysis
is performed done on the entire platform, stock levels and reorder levels can
also be established.
RCDA Principles
There are
several rules governing the application of RCDA to a process. These principles
are found in RCM, but are now drivers for an optimized design. These rules
emphasize the following concepts:
• Design strategy is driven by the consequence of failure, level of acceptable
risk and desired objectives for the overall performance of the process.
• Designs
emphasize mitigating the effect of equipment failure, rather than the failure
itself.
• Operator
intervention reduces the criticality of a system – If the Process Operator in
the field can respond to a failure or anomaly in the process, and mitigate the
effect of that failure, then the system would be considered less critical. This
leads to the next rule,
• Failures of
critical and very important components must be evident to Operators.
• Critical
operating parameters must be evident to Operators. Systems must be in place to
trend and analyze the performance of these parameters.
• Redundancy
greatly decreases the probability of failure and reduces the impact of equipment
failure on the process.
• Maintenance
strategies are in direct alignment with the performance objectives of the
process,
•
Condition-based maintenance strategies are much more cost effective than
reactive (breakdown) maintenance activities,
• Condition
analysis maximizes the useful life of process equipment. This is achieved by
monitoring equipment performance until signs of unacceptable degradation is
detected.
•
Intervention to perform periodic intrusive equipment inspections increases the
probability of failure,
• Many
components exhibit hidden failures, that require periodic functional testing,
• Many
non-critical components can be run to failure if it is not cost effect to
maintain them.
When to apply
Reliability Centered Design Analysis
Reliability Centered Design Analysis is a process integrated into project
management stages i.e. Front End Engineering and Design (FEED). Typical project
management consists of five independent stages. Funding for Reliability Centered
Design Analysis is typically included in Stage 1 of the project CAPEX. Project
RCDA begins in Stage 3 when Process Flow Diagrams (PFDs) and Piping and
Instrument (P&IDs) become available. This occurs prior to final design
selection. This allows change recommendations resulting from the RCDA to be
considered prior to acceptance of final design as opposed to initiating costly
engineering design changes during construction.
The first
step of RCDA is the Process Interview. In the first part of this phase, the
Analyst and platform personnel develop the platform’s operational performance
objectives. In addition, the platform’s various functions are separated into
sub-systems. The purpose of this exercise is to focus the analysis on an asset’s
need to meet the functional requirements of each system on the platform, and to
align the objectives of the maintenance program with platform’s operating goals.
The second
part of step one consists of Process Interviews. The platform’s operating and
technical personnel describe the function of all identified components, using
the platform process system P&IDs. RCDA Analysts facilitated the interviews and
used RCM principles to extract the information required to evaluate the
criticality of the equipment, which is further described below.
The second
step in the analysis is the Criticality Evaluation (also known as Failure Modes
and Effects Analysis (FMEA)), performed by RCDA analysts off-site and reviewed
by the platform core RCM Team personnel on their return visit. In the
Criticality Evaluation, each piece of equipment is analyzed in terms of the
dominant failure modes and the effects of the equipment failure. If the failure
of the analyzed piece of equipment produced effects that were found to be
intolerable, that piece of equipment was termed “critical”. If the failure could
be tolerated, the equipment was termed “non-critical”. Failures resulting in the
inability to accomplish the Operational Objectives were intolerable and thus the
associated equipment was critical.
In general,
the following overall failure effects caused the associated asset to be
classified as critical. The failure has a significant likelihood to result in:
• platform or
system shutdown or reduced throughput
• costly
damage to platform assets
•
unacceptable personnel hazard
•
unacceptable environmental consequence
•
non-compliance with regulatory requirements (i.e. MMS, USCG)
• inability
to accomplish the Operational Objectives
At the
conclusion of the FMEA, a comprehensive report is submitted to the operating
company detailing engineering opportunities. The report includes design
recommendations, which can eliminate or mitigate the effects of failures of
platform systems or system components. At this point the operating company
reviews the design with the engineering firm and takes appropriate action for
re-engineering the system or component design to reduce system or component
criticality.
Reliability
Centered Design Analysis and Front End Engineering and Design
Reliability
Centered Design Analysis is a process, which is integrated into project
management stages i.e. Front End Engineering and Design (FEED). Typical project
management consists of five independent stages. Funding for Reliability Centered
Design Analysis is included in project
RCDA
Methodology
RCDA is a
process. As a process, it follows a uniform set of rules and principles. The
process itself can be seen in the work- flow process diagram.

RCDA Logic
Trees
RCDA uses a
number of logic trees to optimize the design being analyzed. Below is an example
of one of those logic trees. Other trees guide the Analyst through a task
selection process to justify and identify the proper proactive maintenance and
operator tasks for critical components.

Combining
RCDA and Reliability Centered Maintenance (RCM) Stage 4
Combining
RCDA and RCM occurs in stage four of the FEED. In stage four, RCDA
recommendations are reviewed to ascertain if the recommendations were accepted
or another alternative design was selected to eliminate or reduce the effects of
failure of the system. Acceptance of the recommendations requires the Failure
Modes and Effect to be updated prior to performing RCM task selection.
In addition
to the design recommendations, issued for construction P&IDs receive a final
review to ensure the technical content of final revised drawings have been
included the FMEA. Completing the engineering design and P&ID review leads to
performing the RCM task selection. Ideally, the RCM task selection is scheduled
when process equipment and has procured and the Engineering and Procurement
Contractor have received vendor documentation packages.
The final step in the analysis is the selection of tasks. This step is performed
on-site as a joint effort with representatives of each maintenance craft,
operations, and engineering, with RCDA/RCM analysts acting as facilitators for
the task selection process. Each piece of critical equipment is further analyzed
to determine the causes for each dominant failure mode identified in the FMEA.
Proactive maintenance tasks are then identified by the group and assigned to
address these failure modes so that the effect of failure could be prevented.
Tasks are assigned following selection criteria based on performing condition
monitoring, predictive maintenance, or other non-intrusive tasks preferentially
over traditional, time-based intrusive tasks. Using this hierarchical approach
ensures that the most cost-effective program is achieved, since condition-based
tasks are inherently less costly than intrusive tasks.
The next step
was the “Run-to-failure” evaluation for non-critical equipment. Each piece of
non-critical equipment is evaluated with respect to economic considerations, to
determine if cost-effective and applicable proactive tasks should be performed.
If none of the non-critical task justifications applied, the decision was made
to recommend that the piece of equipment be allowed to run to failure (i.e. with
no proactive maintenance) and then repaired when practical. If a component met
one or more of the ”Run-to-failure” criteria for task selection, the same
hierarchical analysis for selecting critical equipment tasks is applied
(non-intrusive, condition monitoring or predictive maintenance tasks preferred
over intrusive tasks). In this way, a complete and optimal proactive maintenance
program is developed based on equipment functionality, providing the platform
with the documentation to prioritize maintenance tasks (proactive and reactive),
identify areas which may benefit from further investigation or modification, and
maintain or improve equipment.
Finally,
because the dominant failure causes are identified for each piece of process
equipment, spare parts requirements are also known for all process systems of
the platform. Stock levels and reorder levels can be then established. Critical
and non-critical components relatively small in size and weight are maintained
on the platform at minimal levels due weight and size constraints. Larger
critical and non-critical spares are typically held within climate-controlled
warehouses on the beach with transportation to the platform provided by
helicopter or boat.
Summary
RCDA has been
successfully conducted on four Gulf of Mexico Deep Water projects and one
international project located in Angola. The analysis has been used to review
over 12,000 pieces of equipment and has provided over 200 engineering
opportunities for consideration. Recommended opportunities include:
• Installing
redundant instruments in basic process control loops (2oo2 voting)
• Installing
blow down connections for critical switches or transmitters, which are likely to
plug with process materials,
• Changes to
software configurations for pre-alarms for operator mitigation, and safe guards
for equipment for start-up
• Equipment
identified as candidates for mechanical integrity programs
• Piping
changes to accommodate maintenance isolation of equipment eliminating equipment
shutdowns with production impacts
• Positive
influence on equipment spare procurement and preservation practices
• Procurement
of state-of-the art technologies
• Reliability
focus versus repair focused organization
•
Implementation of state-of-the art operator mobile data collectors
• PM/PdM
activities for task development prior to commissioning
In addition to applying the principles of RCM in front end engineering and
design of a new projects, the overall reliability efforts has resulted in the
successful development of operational and maintenance strategies for over 12,000
pieces of equipment. |