Sterling operates in a
very lean production environment with limited maintenance
resources. As a result, the maintenance team was focused on work
execution, rather than the proactive monitoring of asset health.
While the company had established a solid enterprise asset
management foundation of planning, scheduling and executing
maintenance work, unscheduled downtime persisted. Sterling
recognized that in order to reduce downtime they needed a
solution to support a proactive approach to maintenance.
While Sterling leveraged
some predictive maintenance technologies, the company was not
fully maximizing the effectiveness of these tools.
Predictive data resided in separate systems and there were
limited resources available to conduct the time-intensive task
of collecting, consolidating, analyzing and acting on the
volumes of condition data resulting from their PdM technologies.
The company required a solution to consolidate this data and
systematically monitor equipment performance and conditions.
In addition, Sterling had
not formally developed technically based maintenance programs
for their critical assets. Much of the maintenance work
conducted was not value-added and did not mitigate the
consequences of failures. Sterling required a work
identification methodology that would allow them to create
technically sound maintenance programs quickly and effectively.
Sterling also recognized
that they would need more than just a quick technology fix to
improve asset reliability. They would require a complete
solution to implement and sustain a disciplined business
approach to maintenance.
The Solution
To achieve its goal of
increased throughput and improved maintenance efficiencies
Sterling Steel selected the Ivara EXP Reliability software
solution.
The solution replaces
traditional reactive maintenance work with technically-based
proactive equipment maintenance programs. By implementing Ivara
EXP enterprise software, Sterling was able to bring together a
wide range of equipment condition data including maintenance
inspections, operator rounds and online information. Sterling
now has a complete picture of their equipment health and
performance - online in real time.
The initiative began with
the development of a business case to establish the
justification and opportunities that existed through reliability
improvements. The business case revealed that significant
financial and productivity gains could be achieved by
implementing the Ivara solution. Once the business case was
accepted by management, Sterling worked with Ivara to define the
scope of the reliability project. During this project definition
phase, the resource requirements, implementation plan, and
measurables of the reliability initiative were established,
providing Sterling with a clear and detailed project roadmap.
A key activity of the
project definition phase is to identify and secure the Core Team
– a cross functional group which act as the internal change
agents for the reliability initiative. The core team includes
participants from maintenance and operations that gather
information from equipment experts to develop maintenance
programs.
With the project plan and
core team in place, knowledge transfer activities began with
Ivara consultants working with management, maintenance and
operations to gain consensus on the detailed process tasks,
roles, responsibilities and training plans required to execute
and support the asset reliability process. In addition, both
leading and lagging metrics were established to help keep
productivity and performance on target.
Knowledge transfer
activities also involved prioritizing assets, assessing the risk
and criticality of each, to identify those that would be
targeted in the reliability improvement initiative. It was
determined that the first implementation would take place
on the crane, a critical asset that was recognized as a
bottleneck in production. As a high tonnage overhead crane,
performance failures could not only result in production losses
but more importantly pose significant safety consequences.
Implementing Ivara EXP
reliability software, Sterling now had an efficient way to
collect, store, display, analyze and manage all maintenance
program and asset health information. Ivara EXP software serves
as the “control panel” for maintenance and operations to manage
the performance of Sterling Steel’s equipment online in real
time, not just analyzing equipment failure, but avoiding it. As
inspection data is collected on electronic handheld devices, EXP
identifies potential failures and recommends the right
maintenance task to be executed at the right time in Sterling’s
enterprise asset management system.
Using Ivara Maintenance
Task Analysis, (MTA) the team quickly developed asset management
programs. MTA leverages historical and readily available
knowledge about the reliability and performance of equipment.
EXP served as the repository for this equipment and maintenance
knowledge – critical at a time where an aging workforce left
Sterling exposed to knowledge loss.

Using MTA, the core team
worked with at the sustaining team to define the maintenance
program of the first targeted asset – the crane. The sustaining
team is comprised of equipment experts that are the most
knowledgeable maintainers and operators of the asset at hand.
Together the core and sustaining teams identified all potential
crane failure modes by reviewing existing PM activities, the
asset’s work history and their own knowledge of the crane. Once
the failure modes were identified, each one was examined to
determine the appropriate action necessary to mitigate the
consequence of the failure.
The resulting tasks were
organized into a complete maintenance program and captured in
Ivara EXP.
With core team coaching,
the sustaining team was then responsible for the execution of
the newly developed maintenance program for the crane. This
included conducting the inspections, utilizing the asset health
dashboard—acknowledging alarms and identifying the right work to
be executed via the CMMS. Once the sustaining team was able to
execute the new reliability program independent of the core
team, the core team began the implementation on the next highest
impact system identified in the asset prioritization exercise.
While the implementation
continues, to-date Sterling Steel has developed asset
reliability programs for several critical assets including the
crane, the arc furnace, and bar mill.
The Results
With the Ivara EXP
Reliability software solution, Sterling Steel has achieved a
significant increase in throughput, through the reduction in
un-scheduled equipment downtime. Downtime at the company’s rod
mill was reduced by 88% and throughput at its meltshop increased
by 30%. The company has adopted a reliability-driven maintenance
strategy that goes beyond planning, scheduling and executing
reactive maintenance work. Sterling is now focused on managing
asset health to support business goals.
Additional benefits
include the following:
• Downtime on the crane is
virtually eliminated, from several times per month to only
minutes of downtime per month. This is a significant benefit
since performance failures on this asset would disable
operations and pose safety risks. The overall reduction in
un-scheduled downtime was 66%.
• Downtime of the arc
furnace, reduced from an average of 5% - 7% per month to 1.5%
per month in only the first 6 months of applying the Ivara EXP
Reliability software solution. This has had a positive impact on
Sterling Steel’s production, while significantly reducing the
cost associated with maintaining this asset.
• Savings in excess of
$100,000 per year due to improvements in the cost of maintaining
belts and bearings of a major system. This is a result of a
re-design driven by the MTA program facilitated by Ivara.
• The Ivara WorkSmart
implementation methodology addressed Sterling’s resource
constraints by focusing on improving reliability one system at a
time to quickly raise the plant’s effectiveness rather than
blanketing all of the assets at once.
• With Ivara EXP, the
collection, storage, display and analysis of asset condition
data is now consolidated and automated. This not only helps
Sterling to better leverage its predictive technology data, it
also ensures a sustainable proactive maintenance approach.
• Since MTA leverages
existing asset performance information, Sterling was able to
quickly and effectively create technically based maintenance
programs for its critical assets utilizing asset data already
available.
• Both maintenance and
operations have a greater understanding of how their assets
function, how they fail and what actions are required to ensure
asset reliability due to the collaborative nature of MTA.
Conclusion
With compensation directly
linked to throughput levels, the Ivara EXP Reliability software
solution is a critical part of Sterling Steel’s long-term
business strategy. Maintenance is now an active contributor to
Sterling’s corporate goals through its focus on reliability. The
asset ‘repair’ culture has been replaced with an asset ‘care’
philosophy driven and sustained by the Ivara solution.
As the implementation
moves forward, Sterling Steel continues to realize the financial
and operational benefits from improved asset reliability.
For more information on
Ivara EXP click here