|
Heavy Duty RCM
Lockheed Martin’s Classical RCM on a 30-Ton Overhead Crane
by
Terry Spychalski, Terry Finnegan, Mac Smith and Tim Allen
When you have a satellite worth 300 million dollars hanging from
your crane hook, there is a very real incentive for safe,
reliable, problem free material handling. Lockheed Martin Space
Systems Company (LMSSC) has more than one hundred cranes lifting
extremely high value, critical flight hardware loads.
These are often one-of-a-kind items and any damage caused by a
handling mishap would have an extremely severe impact on program
cost and schedule. This paper will describe the RCM analysis of
a newly installed bridge crane at the LMSSC site in Sunnyvale,
California and the resulting improvements to the preventative
maintenance program for critical hardware cranes throughout the
company.
Lockheed Martin hired a consultant in 2005 to assess the risks
to personnel and products associated with critical crane lifts.
The resulting report focused on three main areas for
improvement; crane use practices, operator skills training and
crane suitability and reliability.
The first two issues have been addressed by a restructuring of
the LMSSC crane operator training program. Three levels of
operator training have been created. A Level I operator can only
lift non critical loads. A Level III operator is trained to be
part of a team executing step by step written critical lift
procedures led by a lift director.
A Crane Operations Review Team was formed to implement the
consultant’s recommendations. The CORT team evolved into a
company wide Crane Risk Reduction Department dedicated to
improving crane operations.
The study of the suitability and reliability of these cranes has
focused on achieving consistent configuration control throughout
the lifetime of each crane with proper design, maintenance and
documentation. The CORT team developed a design standard for
critical cranes that incorporates many enhanced safety features
developed for the nuclear and aerospace industries.
Fail-safe and redundant components have been added to prevent
dropping the load in a catastrophic failure in the load bearing
systems. Each one of these added devices introduces the risk of
downtime if they are not properly maintained. An analysis of the
existing crane maintenance practices showed that these critical
cranes were not maintained differently from non-critical cranes.
The enhanced safety features and their control systems were not
addressed in the generic PM checklist.
It was decided to take a recently installed crane with many of
the features of the new design standard and perform a pilot
study using the Reliability Centered Maintenance method to
tailor a PM program specific to critical lift cranes.
The Crane RCM Program
Historically, the 120 critical cranes throughout the Space
Systems Company developed their PM tasks via an evolution of
experience with some inputs from the OEMs. However, management
of the Crane Risk Reduction Department recognized a need to
upgrade the crane design standard and also to initiate a formal
process to revisit and upgrade the crane PM program.
The Classical RCM process had been previously used in a recent
SSC project with a critical milling machine.
The RCM process was selected here based on the successful
experience and results with that machine and other industrial
applications.
The
Classical RCM process is so named because it follows and
conforms to the original methodology developed for the 747-100
airplane. It is a 9-Step process (see Figure 1) where the four
fundamental principles of RCM are addressed in Steps 4, 5, 6 and
7. A detailed discussion including a fully developed example and
a review of seven actual case studies is given in Reference 1.
This article reports on the results of Steps 1 to 7, the Systems
Analysis portion of the process.
The contractor has achieved success with Classical RCM over the
past 25 years by using a team approach to the analysis.
Specifically these teams must be composed of craft technicians
and engineering specialists who operate and perform the hands on
maintenance of the selected equipment/systems plus a facilitator
who is an expert in the application of the RCM methodology. This
approach was followed here, and once again proved to be the
right combination to produce a significant amount of new
information to upgrade not only the PM program content, but also
a series of new inputs to the design standard and operating
procedures.

The analysis was done by dividing the Crane System into four
Subsystems as shown in Figure 2. The lines between the
subsystems indicate the functional in/out interfaces where the
out interfaces define the Subsystem functions to be preserved
(Step 4). A Failure Mode and Effects Analysis was then performed
on the components in each Subsystem to pinpoint exactly what
failure modes could potentially produce a Functional Failure
(Step 5). Each failure mode was then put through the Logic
(Decision) Tree Analysis (Step 6) to assign a specific level of
criticality; including hidden if applicable.
Finally, critical failure modes were assigned applicable and
effective
PM tasks and non-critical failure modes were given a formal
Sanity Check to evaluate whether they could be Run-To-Failure
(Step 7). The results of this analysis are summarized in Figure
3, the Systems Analysis Profile.
The detail that was achieved by the team is reflected in the
large number of individual components and the analyzed failure
modes (45 and 137, respectively). It is especially important to
note that 9 out of every 10 failure modes were critical from
either a safety and/or outage point of view. Thus, a focused PM
program becomes very necessary to mitigate safety risks and
preserve the crane availability for use and reliability for
actual operation.
Notice also that 1 in 6 failure modes are hidden from the
operator and pose a special risk concern if not properly
treated.
RCM Program Results
Figure 3 identified 168 PM Task Decisions and we will now
discuss the specifics of those decisions. An important part of
this discussion includes a comparison between the RCM-based PM
tasks and the conventional (pre-RCM) tasks. Since the crane used
in the Pilot study is a new installation, a formalized
conventional PM program had
not
been specified. So the team, as a part of the pilot program,
developed a “Straw Man” list of PM tasks. Basically, three of
the most experienced technicians on the team took existing
component level tasks that were already documented from current
operations and applied their collective tribal knowledge to
define the component Straw Man list.
This Straw Man represents the PM program that would have been
used, absent RCM, and is thus a very reasonable set of data for
the comparison.

Figure 4 shows the breakout at the failure mode level of the 168
decisions by PM task type, including RTF for the RCM results and
none for the Straw Man (i.e. with the Straw Man, deliberate
decisions were not made to exclude any PM action). The striking
thing here is the number of active tasks for each profile is
nearly identical (105 vs. 90). In fact, the total Time Directed
tasks for each profile is identical at 85. From a PM Task Type
point of view, the RCM analysis was moderately successful in
introducing some Condition Directed Tasks (PdM) where none would
have otherwise been specified, and did increase the Failure
Finding Tasks by 50% since we knew from the analysis exactly
where the most significant hidden failure modes were located.
However the really
important benefits from the RCM process are revealed in Figure
5, the PM Task Similarity Profile. Here, we see five specific
statements which characterize where similarities or differences
exist between RCM and Straw Man PM tasks. Notice that from a
decision point of view only 1 in 5 (20%) tasks were identical.
By default another 1 in 4 (24%) appeared to be identical where
RCM
specified RTF and the Straw Man had no task defined, but this
was only by luck in the case of the Straw Man profile.

The arrows in Figure 5 indicate the three areas where the
beneficial impacts of the RCM process are most strongly felt:
1. 30 PM tasks (18%) were modified versions of the Straw Man
tasks. Here the RCM analysis changed the task frequency (mostly
by increasing the interval) or by increasing the basic scope of
the Straw Man task.
2. 39 PM tasks (23%) were added by the RCM analysis where none
existed in the Straw Man. This was made possible by the fact
that we knew, at the failure mode level, where the critical
failures could occur. The Straw Man never went to that level of
definition.
3. Conversely, 25 PM tasks (15%) were designated RTF by the RCM
analysis where the Straw Man would have spent resources to do a
task. Again, we knew where the non-critical failure modes
resided and could thus specify RTF without any risk. Overall,
the RCM recommendation changed the Straw Man plan by 56%.
Lessons Learned
This study provided many opportunities for improvements to
LMSSC’s crane maintenance program and critical crane design
standards. We were able to use information from the study to
eliminate unnecessary, intrusive maintenance tasks and add tasks
which specifically addressed the enhanced safety systems of our
critical cranes. This will provide a more focused approach to
maintenance and make better use of the time spent by the
maintenance staff.
The “Items of Interest (IOI)” feature of the RCM software was a
very valuable tool. It enabled the team to document points
brought up in the course of discussion that were not directly
related to maintenance issues. We have taken these lessons
learned and applied them to our critical crane design standard.
Design changes will make new cranes easier to operate, service
and maintain.
For example, the detailed analysis of the hydraulic emergency
drum brake system sparked discussion that has led to design
changes that will greatly reduce the chance of clean room
contamination and still prevent a load free fall.
Another IOI indicated a need to establish crane maintenance
metrics so that trends can be properly measured and evaluated.
Other IOI’s showed the discrepancy between what was wanted for
this crane and what was actually provided. This has led to
better clarification of the details in the design standard and
improvements to the control systems and operator interfaces.
Many improvements to the Lockheed Martin Space Systems Company
critical crane maintenance program and design standard were
identified as a direct result of the Reliability Centered
Maintenance study on this crane.

Where To Go From Here
Now that we have completed the Classical RCM Process for one of
our critical cranes, developing a solid implementation plan
becomes the center of our focus. The fact that our maintenance
organization has experience with other projects is a significant
benefit.
Move to CMMS
The first step is writing RCM maintenance tasks descriptions for
this specific crane and then loading them into the CMMS. This
requires sorting tasks by frequency and performing craft
personnel in preparing necessary work orders. The process is
made easier thanks to the flexibility of the software which
automates this sorting. The second step is to create
maintenance tasks for the remaining 120 critical cranes applying
the RCM template. We are comfortable with this approach because
our critical cranes’ designs and features are very similar.
The significant differences are enhanced safety features such as
drum over speed brakes and motor controls.
Maintenance Training
After many years of applying the same crane maintenance template
to all systems, it’s important to ensure that the maintenance
team is properly introduced to RCM and is trained on all new PM
tasks. We are planning a training session with crane maintenance
crew members from both Sunnyvale and Denver. It will include an
introduction to RCM and provide actual hands-on training while
performing the new PM on the subject crane.
Maintenance Staffing
The RCM team was concerned that the RCM maintenance program
might create the need for a significant increase in manpower.
When the team analyzed the differences between the current PMs
and RCM PMs, considering the new tasks, deleted tasks and RTF
decisions, they arrived at an estimated increase of one
technician. Managers will be closely tracking actual hours for
accurate manpower planning.
Items Of Interest (IOIs)
The team made excellent use of this part of the RCM process.
Again, the software is designed to easily track each item. We
will continue to maintain focus on these valuable observations
especially when they affect design standards.
|