Focal Points: Sponsored links

New CMMS! MVP Plant - Smart Software for Smart Maintenance

 Join The Association For Maintenance Professionals

RCM-EAM-MTrain-2009 Daytona Beach 

Infrared windows and safety products

Follow us on Twitter



 

 

 


Return to Home Page

Overall Equipment Effectiveness by Bob Hansen (Excerpt Chapter 6)
Win-Win Maintenance/Equipment Shutdown Strategies (Page 4)

4. After the energy high has worn off, energy levels usually deteriorate over time into fatigue. People then concentrate poorly. They make more mistakes and miss opportunities to catch problems during this low energy time. 

Regarding the shutdowns themselves, I learned that no two shut-downs are the same. Each one is a new project. Like projects, shutdowns are executed better if they start on time, everyone is synchronized, and everyone is fully informed. Uncertainties arise in nearly every shutdown; they often multiply relative to the calendar length of the shutdown. Local mechanics, technicians, and engineers, dedicated to the site and knowledgeable of the specific equipment and processes, are the best resources for doing the work, especially the critical, non-routine work. Because many of the upgrades have been developed internally, they should be implemented by those individuals responsible for the upgrade.

Learning curve studies indicate that repeat and similar maintenance work can be completed faster by using the same people each time. Usually these people are the local resources who get involved each time. We will call the local work area mechanics dedicated to the equipment and processes, key mechanics.

Given these general observations, it was clear that more frequent short shutdowns would be beneficial for the work area. My next step was to develop a plan that was workable for both production and maintenance. By intuition, a strategy began to emerge.

Critical Chain¹ by Eli Goldratt was not yet available at the time, however, it is now apparent that the strategy was consistent with the theory of constraints (TOC), as presented in his 1997 book. Critical Chain explains the steps and power of addressing Shutdown TOC. It also supports the principle that without attention to detail, most task estimates are inflated significantly.

The annual operation is like a critical chain. Shutdown events, just like production time, experiment time, and process verification time, are all part of the annual timeline. A shutdown must be treated as the critical chain's priority event during its execution. If this is accepted, the total community will assist in supporting the success of the shutdown through minimal time and good startups. Each shutdown includes several TOC components. These can be called: identify, exploit, subordinate, elevate, and go back.

Identify.

The first step in a shutdown is to identify the key constraint. In this example, as is the case with many maintenance organizations staffed primarily with shift mechanics, the key constraint was the availability of the local resources. These key mechanics are extremely valuable in that they know: the process, the equipment, the operation systems, and the geography of the building. People coming to help from other areas would not be as effective as the local people with local knowledge. Operators with mechanic skills can also be very useful and should be part of the resource base. Keep in mind that the cost of using local resources is already covered in the maintenance operating budget.

Next Page>      Page 1/2/3/4/5/6/7/8/9/10/11/12/13/14/15/16/17/18/19/20

Advertisement

Click here to return to Home Page