Focal Points: Sponsored links

MRO-Zone.com - Maintenance Focused Search Engine

Find a Reliabilityweb.com Maintenance Conference
iPresentation Tutorials - quick lessons from experts
ReliabilityRadio.com - The Voice of Maintenance




Return to Home Page

Overall Equipment Effectiveness by Bob Hansen (Excerpt Chapter 6)
Win-Win Maintenance/Equipment Shutdown Strategies (Page 10)
These improvements were very good. However, the maintenance foremen were confident that short frequent shutdowns and maintenance linestops would allow for high energy levels and improved focus, leveraging individual productivity. The newer approach would prevent the pitfalls of multi-tasking and student syndrome. With multi-tasking, a key resource rotates among several jobs, doing a little portion on each and taking longer to complete them all. Student syndrome is the tendency to start jobs late when work estimates are conservative; this happens if details are not well thought out causing estimates to be vague. By avoiding these problems, the foremen consciously lowered the estimates of the time needed to complete many tasks.

The foremen proposed four 3.5-day shutdowns and ten maintenance linestops for the annual plan. This request was entered into the forward 12-month production plan. The linestops were spaced approximately one per month. The shutdowns were evenly spaced about two months apart and avoided a seasonal volume increase.

This plan would require a total of 4 X 3.5 days + 10 X 0.5 days = 19 shutdown days; it would represent an improvement of 9 to 9.5 production days per year because some product changeover time would also be reduced.

With this strategy, the number of shutdown work hours a key mechanic could complete would improve to 4 X 39.5 hours + 10 X 9 = 248 hours relative to the total shutdown time of 19 X 24 hours = 456 shut-down hours for a mechanic work ratio of 54 percent.

248 work hours
456 hours total

= 0.54 or 54 percent. = 1.47

The increase in the key mechanic work ratio from 38 percent in the original plan to 54 percent in the revised plan is an improvement of 42 percent for the key resources.

54 percent
38 percent

=1.42

With this plan more of the original shutdown work would be accomplished by the existing work area mechanics by completing the external non-shutdown work between planned downtimes.

The original strategy requires 4000 hours of overtime and about 7200 pay hours from external resources. The revised strategy results in 2440 hours of overtime and 4100 pay hours from external resources. Just imagine the improvement in this area’s annual maintenance budget which directly flows into operating income.

Furthermore, the number of shutdown days was reduced from 28 to 19. If this plan was accepted, annual production could be increased by 2.5 percent. All in all, the revised plan represented a significant win-win strategy for the plant.

Next Page>      Page 1/2/3/4/5/6/7/8/9/10/11/12/13/14/15/16/17/18/19/20

Advertisement

Click here to return to Home Page

 
List Your Web Site Editorial Policy Privacy Policy Contact us
Feedback © Copyright 2000-2006 NetexpressUSA Inc. All rights reserved Terms of Service Trademark Notice