23.
Think through how to communicate during the shutdown.
Many areas have found radio communications at each job
location to be very beneficial.
24. Check whether the right
materials and spare parts are on site before the
shutdown begins. Otherwise, cancel that task.
Eliminate all surprises.
25. Determine the kind of
training that production, maintenance, and support
groups will need, given the new modifications.
Schedule this activity to be held before or if
necessary, during the shut down. The crews and
mechanics will need to be up-to-date when they use the
modified equipment for the first time.
26. Always provide a back-up
resource, equally familiar with the tasks, for
critical technical skills on key projects. Avoid
having only one person for any critical key job during
the shutdown. The first person may be too exhausted
from completing the job to commission the work. Then,
if problems develop, that person is required to do
even more, leading to a cycle of mistakes and
confusion. In this scenario, the entire site could be
at risk if the system isn't operational. A second
resource can verify the work and increase factory
effectiveness by alternating shifts during the
commissioning phase.
27. Break all jobs and blocks of
work down to their smallest increment. Smaller parts
of projects can then be implemented over time.
28. If possible, design project
work and system modifications so that the original
equipment conditions can be restored if the new design
fails.
29. If several similar pieces of
equipment are to be upgraded, work on only one
initially. Confirm that the expected results have been
achieved before changing the rest.
30. Use short, frequent
linestops as the most effective way to perform routine
maintenance and predictive maintenance checks. All day
crews should be mobilized to provide assistance during
the linestops. Complete all routine PMs during normal
linestops. Use the shutdowns for major work.
31. Prior to the shutdown,
complete all predictive monitoring tasks to assess the
current condition of the equipment. Schedule only
those things that require intervention. Take notes and
measurements for historical reference on items that
may change during the shutdown. Then, original
conditions can be reestablished, if necessary.