|
The Origins of
Maintenance Problems
The Design and
Commissioning Phase
Maintenance engineers
commonly deal with the result of someone else's design
- whether good or bad. When design is finished,
construction starts and finishes, and the plant is
commissioned. The Maintenance Engineer arrives someway
through this (if he is lucky). Quickly he finds
himself left with a maintenance budget being used to
finish off construction / over-expenditure, a plant
that is going through teething problems, spares
arriving in dribs and drabs and little information
about plant failure modes and the effect of failure.
Rarely is the plant delivered to the maintenance
department with a comprehensive and well-documented
maintenance requirements analysis and a maintenance
plan.
What happens in best
practice organizations is that, amongst other things,
a fully documented RCM based maintenance program is
developed through the design phase. Unfortunately in
the vast majority of capital projects in industry, any
reliability engineering or failure analysis is done in
an informal manner and certainly not provided to the
maintenance department for use in developing asset
management strategies and policies.
Post Commissioning
After commissioning,
(or sometimes before) the design team disbands and its
members find work on new projects. The Maintenance
Engineer is left to second guess the design intent,
the plant limitations, the potential failure modes,
and the likely consequences of them. The operations
people are, at the same time, learning how to operate
the plant and experimenting with it; pushing it to its
limits and occasionally well over its design intent.
There is limited money or time to change obvious
design or maintainability problems in the new plant.
The task of defining
the plant maintenance policy¹ is
a priority but a most daunting one. Whatever is
achieved is done in a rush often using people in an
opportunistic manner. The problems that emerge right
from the beginning will be as follows:
- There is no
consistency of analysis philosophy.
- Maintenance
personnel, being risk averse, write maintenance
policies which over service and use overhaul or
intrusive methods as a means of prevention - often
to the detriment of reliability rather than for
its good² .
- There is no audit
trail, and only those who wrote the policies know
their rationale. It becomes near impossible to
review the program and objectively assess its
effectiveness.
Full Production
When the plant swings
into full operation and breaks down, more maintenance
tasks are created and some existing tasks are done
more frequently. Many of these new tasks duplicate
others. Often, in an attempt to be seen to be doing
something about high profile reliability problems,
maintenance personnel create and perform tasks
supposed to prevent the failures but, in reality,
serve no realistic purpose.
Soon the Preventive
Maintenance (PM) requirements exceed the labor
resource available. PM is missed, preventable failures
occur and unplanned maintenance work consumes more
labor than necessary. The number of temporary repairs
grows out of control and the costs of revisiting them
or repairing additional damage caused by them wastes
more resources.
The vicious circle of
breakdown maintenance, temporary repair, and reduced
PM gains momentum and becomes well entrenched.
Management Consultants
(often with a cost reduction focus) arrive on site and
cut staff numbers and budgets. This serves only to
tighten the vicious circle and increase the rpm. The
end result is typically a large morale problem for the
maintenance department and a poorly performing plant.
Many organizations have
tried to regain control by using RCM to develop their
maintenance program. This is often a pursuit with
limited scope and a high failure rate. This is because
RCM is highly inefficient when used as a
rationalization tool. It consumes excessive amounts of
the most valuable resources on site - those being the
scarce maintenance and operations personnel.
A large element of the
inefficiency of RCM, is that it does not acknowledge
the experience and value of the current maintenance
program. It starts from scratch and builds a
maintenance program from the function down.
The high failure rate
of RCM amongst mature operations is not surprising
when it is realized that RCM was developed by Nolan
and Heap (Nolan and Heap, 1978) for use in the design
phase of the equipment life cycle (Moubray 1997). It
was not designed for use in mature industries as a
rationalization tool.
Improvement Tactics
The Dupont Experience -
Four Common Strategies
In this predicament,
case studies and experience suggest that, outside of
cultural and behavioral initiatives, asset managers
should be focusing on a few key areas. They must:
- Develop focused
maintenance policies,
- Improve planning and
scheduling based on the revised policies, and
- Focus on defect
elimination.
The Dupont model of
Up-Time featured in the Manufacturing
Game® illustrates these points very well. The
table below illustrates how Dupont has modeled the
relative effect of various strategies on plant uptime.
¹A
maintenance policy is the combination of what is to be
done, how frequently and by whom.
²Particularly
if the maintenance is intrusive.
Click
here for page 4 |